May 04, 2023 The number and arrangement of the injection nozzles per lubrication station are usually constant. In addition to the control of all existing valves, it is possible to change the positions of the injection nozzles in the cross-section at successive lubrication stations in order to realize an almost uniformly distributed lubricant injection at the pipe circumference [Schoesser2013]. (Image: Detail - Injection nozzle) (Image: Arrangement of injection … |
|||||
The number and arrangement of the injection nozzles per lubrication station are usually constant. In addition to the control of all existing valves, it is possible to change the positions of the injection nozzles in the cross-section at successive lubrication stations in order to realize an almost uniformly distributed lubricant injection at the pipe circumference [Schoesser2013]. (Image: Detail - Injection nozzle) (Image: Arrangement of injection … |
|||||
Rolling is the rotation of jacking machines and jacking pipes around the jacking axis. In the case of circular cross-sections, these are harmless to the subsequent pipeline as they do not impair its function. During jacking, however, and especially in the case of long and curved jacking, this rolling can become problematic due to the installations in the pipe string. In order to avoid rolling, plates are attached to the left and right on the jacking … |
|||||
Today, supply and discharge lines are still predominantly installed by using the open-cut method: a trench is dug, the lines are installed. Under the protection of an embankment or sheeting and the trench is filled afterwards. In the face of the numerous disadvantages as well as the citizens' growing environmental consciousness in the future it is urgently necessary to take trenchless technology into account much stronger than until today as an alternative … |
|||||
May 04, 2020 Method of operation and sequence Microtunnelling with auger spoil removal is characterized by the jacking of pipes in soils with simultaneous excavation of the working face using a cutting head and by continuous removal of the spoil with a spiral conveyor or auger, which is guided inside a spiral conveyor guide pipe, towards the starting shaft. (Image: Technical components for microtunnelling with auger spoil removal in single phase jacking) (Image: … |
|||||
(Image: Equipment, possible arrangement of the components on the construction site and space requirement (approximately L × W = 22.0 × 4.0 m) in microtunnelling with auger spoil removal - top view (on the model of the jacking of pipes DN/ID 600, pipe length 2.0 m)) The dimensions of the starting shaft are determined by the type of machine and the selected size and length of the jacking pipes. Today, use is made mostly of prefabricated reinforced concrete … |
|||||
|
|||||
May 04, 2020 (Image: Microtunnelling with auger spoil removal in single phase jacking - Variant: driving the cutting head with the spiral conveyor) (Image: Microtunnelling with auger spoil removal in single phase jacking - Variant: direct driving of the cutting head and separately driven spiral conveyor) Drive variants of the cutting head:
|
|||||
|
|||||
May 04, 2020 (Image: Example of cutting head driven with the spiral conveyor [Becke96]) (Image: Example of cutting head driven with the spiral conveyor [FI-Herreb]) (Image: Example of cutting head driven with the spiral conveyor [FI-Wirthb]) (Image: Example of cutting head driven with the spiral conveyor [FI-Schrö]) |
|||||
|
|||||
|
|||||
May 04, 2020 Possible measures for the application in groundwater-bearing soil:
|
|||||
Compressed air valve inside spiral conveyor guide pipe with longitudinally displaceable cutting head(Video: Technique SANWA HORIZONGER for the application in groundwater) |
|||||
|
|||||
May 04, 2020 |
|||||
May 04, 2020 (Image: Microtunnelling with hydraulic spoil removal in single phase jacking) (Image: Basic equipment, possible arrangement components on the construction site and space requirements (ca. L × B = 35 × 4 m) for microtunnelling with hydraulic spoil removal - plan view (on the model of the jacking of pipes DN/ID 600, pipe length 2.0 m)) Method of operation and sequence Microtunnelling with hydraulic spoil removal is characterized by the jacking of pipes … |
|||||
(Image: Basic equipment, possible arrangement components on the construction site and space requirements (ca. L × B = 35 × 4 m) for microtunnelling with hydraulic spoil removal - plan view (on the model of the jacking of pipes DN/ID 600, pipe length 2.0 m)) The dimensions of the starting shaft are determined by the type of machine and the selected size and length of the jacking pipes. Today, use is made mostly of prefabricated reinforced concrete … |