Bothar’s cutting head innovation
Apr 26, 2024
The trenchless industry in Australia continues to grow and the need to provide customised solutions becomes vital for a leading subsurface contractor.
Recognising the need for advanced solutions to meet the growing demands of modern infrastructure projects, Bothar Boring has led the way in the innovation department with its vast fleet of in-house designed and fabricated ‘Bothar Built’ equipment. Now, the company is breaking new ground with its latest specialist-built cutting head. Bothar has an exceptional team of industry leading experts and equipment manufacturing specialists that turn ideas and concepts into cutting-edge solutions to overcome limitations of conventional methods.
In recent times, Bothar has experienced an increase in requests for installations where there is an inability to provide a retrieval shaft. Bothar refers to this practice as ‘blind boring’ and it had been an obstacle on the company’s radar for some time. When the company was approached for advice on providing a suitable method to install 19 x 102m canopy tubes under a live railway without the ability to use a retrieval shaft, the team was confident they could deliver. There are limited trenchless methods which could deliver accuracy over such lengths.
As such, Bothar embarked on a mission to develop an innovative solution to directly install the required 500mm steel case, in rock up to 60Mpa without an exit shaft, with pinpoint accuracy, while ensuring the ground was always supported. The result was a custom designed specialised bi-directional retractable cutting head which hadn’t been utilised on this size of installation. Using Bothar’s in-house design and fabrication facilities, the cutting head was designed, built, and tested within a matter of weeks. The experimental cutting head was deployed to site and proved to be extremely effective. The tight program constraints meant that Bothar had to install two canopy tubes at a time, adding additional complexity to the delivery. Bothar successfully completed the canopy tube installation and was able to accelerate the pace of the project with its bespoke cutting head.
The unique cutting head consists of three 13 ¾-inch and three 9-inch tri-cone type TCI cutters on a 50mm backing plate with water portability and outer cutters spring loaded on a 40mm greaseable solid bar hinge. A laser guided vacuum system was used to achieve tight design tolerances at significant lengths. The modified head was developed to ensure the tunnel is always supported by the installation of steel casing in the unlikely but possible case of ground movement. The cutting head has since been used successfully on several projects in adverse, mixed ground conditions up to 200Mpa. Furthermore, tackling other obstacles such as ‘blind boring’ into service manholes is now no problem with the use of this cutting head, changing the landscape of underground construction. Bothar’s ability to utilise its vast trenchless experience to innovate such a design is backed by its inhouse workshop facility. This gives Bothar Boring an additional advantage in the ever-evolving trenchless arena for future works.
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
bothar Boring & Tunneling
98 Ingleston Road
QLD, 4154 Wakerley
Phone:
+61 1300 807 000