Singapore: tunnelling for sewage superhighway completed
Jan 12, 2024
Milestone for the epoch-making "Deep Tunnel Sewerage System" (DTSS) project in Singapore: the five contractors have completed tunnelling works for the second construction phase of the gigantic sewer pipe system.
The final breakthrough took place in July 2023. A total of 19 Herrenknecht tunnel boring machines (TBMs) had excavated and lined some 49 kilometers of tunnel since 2019. In addition, a Herrenknecht Vertical Shaft Sinking Machine (VSM) was used.
As an island state, Singapore obtains a significant portion of its water supply from state-of-the-art rainwater and used water treatment. Back in the 1990s, Singapore’s National Water Agency, PUB launched a massive project to strengthen the nation’s water security: when completed, the "Deep Tunnel Sewerage System", or DTSS for short, will include a total of approximately 200 kilometers of newly built sewers running up to 60 meters deep underground. It is designed to meet Singapore’s long-term needs for used water collection, treatment, and reclamation.
This underground system collects used water from homes and industries and conveys it entirely via gravity to state-of-the-art water reclamation plants without the need for additional pumping stations. The newest of these is currently being built in the Tuas industrial area and will have a capacity to treat of up to 800,000 cubic meters of sewage per day.
Phasing out the intermediate pumping stations and other aged used water infrastructure will also free up around 150 hectares of land in the densely populated metropolis (around 8,750 inhabitants / square meter), for higher-value use. Marking the completion of tunnelling works, Goh Si Hou, Chief Executive of PUB, said: “As one of the most water-stressed countries in the world, the ability to effectively collect and recycle our used water in a closed water loop has been a game-changer in our quest for water security.
The Deep Tunnel Sewerage System is not only an engineering feat, but a key pillar in strengthening Singapore’s water resilience to meet the long-term challenges of climate change and growing water needs."
49 kilometers of tunnel for DTSS 2
PUB is implementing the DTSS project in two phases: in Phase 1 (DTSS 1), between 1999 and 2008, 48 kilometers of main tunnel and 60 kilometers of link sewers were constructed in the eastern part of Singapore. Back then already, five Herrenknecht EPB Shields excavated 28 kilometers of tunnel. The second phase (DTSS 2) is now extending the system in the south and west of the main island by a further 100 kilometers of sewers, of which just under 49 kilometers were excavated by tunnelling machines from Herrenknecht. Construction for DTSS 2 officially began in April 2019. The five contractors involved completed tunnelling in the summer of 2023. DTSS 2 is expected to be operational two years from now.
Herrenknecht TBMs defy complex geology
With Herrenknecht TBMs having proven themselves in Phase 1 already, in the second phase of the project the decision makers for all five construction lots once again opted exclusively for mechanized tunnelling technology from the manufacturer in Schwanau in the south of Germany. 18 Mixshields and one EPB Shield (Earth Pressure Balance Shield) with diameters between 4.50 and 7.56 meters were used to bore the sewage collectors and line them with segments. Herrenknecht also supplied 12 separation plants for the Mixshield drives and provided comprehensive support services throughout the entire project. This included, for example, remote access to individual machines, enabling them to be monitored and controlled remotely.
Among the challenges for machines and miners was the city state's complex geology. The "Jurong Formation," for example, consists of sandstone, siltstone, mudstone, limestone, dolomite and some conglomerate, which are extremely folded due to tectonic plate movements.
As a result, diverse rock types with different weathering grades often alternate along a tunnel alignment and even in the cross section of a tunnel. "In close cooperation with the customers, we therefore adapted the design of the TBM to the complex geological conditions," explains Dirk Schrader, Herrenknecht's General Manager Asia Pacific. Special solutions were also required for construction of five of the 24 shafts in Tunnel Contract T-11 with diameters between 10 and 12 meters.
In this particular section, with depths of up to 60 meters there was high water pressure the shafts constantly had to withstand. "For this reason, for the first time in the Asia-Pacific region, a Vertical Shaft Sinking Machine (VSM) from Herrenknecht was used for sinking the shafts," elaborates Schrader.
More News and Articles
Jul 24, 2024
News
UK utilities place multiple orders for settlement tank technology
Northumbrian Water, Southern Water, and Dŵr Cymru upgrading wastewater sites
Three UK water utilities have agreed orders for the installation of a total of six conical settlement …
Jul 22, 2024
Article
Reusing wastewater, rethinking water: Maharashtra's roadmap
How Maharashtra turns wastewater into a resource
Water resource management is a critical issue globally, and in India, the state of Maharashtra is pioneering efforts to regulate and …
Jul 19, 2024
News
Kansas City advances fire hydrant leak detection technology
An acoustic fixed-base pipe monitoring technology that uses fire hydrants to host multi-sensor devices, has already found more than 30 leaks for Kansas City Water, says Lou Rossetti …
Jul 17, 2024
News
When two bores right a wrong
The Edge Underground team is adamant: there is always a risk of things going wrong on a trenchless project, even for the most prepared contractor.
Experience and having the right equipment can be the difference between …
Jul 15, 2024
News
Adapting to a region’s growing water and wastewater needs
Gippsland Water has completed two major projects to provide local communities with water security. Trenchless Australasia takes a look at the two projects helping increase water supply …
Jul 12, 2024
News
Connections made in Glastonbury
Difficult ground conditions called for a specialist solution when new PE pipes for potable water services had to be installed underneath two, 10-metre road crossings in the grounds of the UK’s ultimate music festival …
Jul 10, 2024
Article
The Water-Energy Nexus: Interdependence and Challenges
Niclas Andersson, CEO of AirWater2All, explains the connection between water and energy. The importance of this connection and the areas in which it needs to be considered are explained …
Jul 08, 2024
News
Minimising cultural impacts with trenchless technology
Yarra Valley Water is leveraging the benefits of trenchless technology to lessen impacts on the Upper Darebin Creek branch sewer project.
The project consists of building a 2.7km sewer pipe …
Jul 05, 2024
News
SprayWall: Reinforcing Underground Infrastructure with Unmatched Strength
In the trenchless technology industry, finding a rehabilitation solution that offers ease of installation and exceptional structural integrity is paramount.
For three decades, …
Jul 01, 2024
News
“Don’t let stereotypes hold you back”
Trenchless Australasia sat down with Rob Carr project manager Marie Piette to discuss her career and work at the microtunnelling contracting company.
From Norway to Cambodia and now Perth, Western Australia, …
Jun 28, 2024
News
Transforming Wastewater: Towards Climate-Neutral Sewage Treatment
Baden-Württemberg’s Minister President Winfried Kretschmann recently toured the Büsnau Training and Research Sewage Treatment Plant, where a pioneering project led by researchers …
Jun 26, 2024
News
Bothar advances with significant new contracts
Having commenced work on the Fitzroy to Gladstone Pipeline earlier this year, Bothar Boring and Tunnelling has announced the award of further contracts as part of its ongoing collaboration with …
Contact
Herrenknecht AG
Schlehenweg 2
D-77963 Schwanau
Germany
Phone:
+49 78 24 30 20